General Description - The work to be performed under this contract includes removal and replacement of
existing concrete including crosspan, sidewalk, curb and gutter, curb ramps. Perform full depth reclamation,
and various thicknesses of asphalt paving within the street(s) listed in the Appendices or as directed by the
Project Manager. The Contractor shall supply all labor, equipment, and materials necessary to complete the
work in accordance with these specifications. The contract shall be awarded based on bids received for Bid
Schedule A and the contract documents. Work on Mikelson Blvd shall begin May 30, and completed
before July 14, to avoid school traffic issues. Contractor will be required to coordinate construction
activities with adjacent businesses, trash removal companies, school district, HOA, Metro Districts, and other
Town maintenance projects if applicable. Contractor shall acquire all Town of Castle Rock and State of
Colorado stormwater permits as applicable, approved TESC plans will be provided after notice of award is
issued. The contractor shall commence work no later than three (3) calendar days from, and including, the
date of the Notice to Proceed, and be construction complete (punchlist items, cleanup, and demobilize) within
one hundred and sixty days (160) working days from the date on the Notice to Proceed. If “Construction
Completion” is not issued within the allotted contract time for the original scope of work, “Liquidated
Damages” shall be assessed. When contract work is complete, the contractor shall commence work on
punchlist items, cleanup, and demobilizing regardless of contract time remaining. Work shall take place
between April 3, 2023 and November 3, 2023. A schedule of sequencing of all work shall be submitted at or
before the project pre-construction meeting, and approved by the Town prior to issuance of Notice to
Proceed.