General Description - The work to be performed under this contract includes removal & replacement of
asphalt mat, heating & scarifying, milling of asphalt pavement, asphalt pavement overlay, Full Depth
Reclamation and the application of Seal Coat (GSB 88), crack seal, mastic. The removal & replacement of
sidewalk, curb & gutter, and concrete pavement and silicone sealant. The Contractor shall supply all labor,
equipment, and materials necessary to complete the work in accordance with these specifications. The
contractor shall adhere to the Town’s Temporary Erosion and Sediment Control (TESC) manual for all stages
of the project. The contract shall be awarded based on bids received and the contract documents. A
schedule of sequencing of all work shall be submitted at or before the project pre-construction meeting, and
approved by the Town prior to issuance of Notice to Proceed.
“Founder’s Fire Station #153” Concrete work and asphalt full depth reconstruction shall be completed in a
manner to maximize access and parking and shall take place during normal weekdays from 7a.m. - 5p.m.
Asphalt paving and concrete pavement removal & replacement shall be completed in two (2) phases, asphalt
paving and concrete work shall not take place simultaneously. All work must be coordinated with Fire
Department staff.
“Prairie Hawk Fire Station #154” Concrete work and asphalt milling shall be completed in a manner to
maximize access and parking and shall take place during normal weekdays from 7a.m. - 5p.m. Asphalt paving
and concrete pavement removal & replacement shall be completed in two (2) phases, asphalt paving and
concrete work shall not take place simultaneously. All work must be coordinated with Fire Department staff.
“Ray Waterman Treatment Plant” work shall take place during normal weekdays from 7a.m. – 5p.m. Concrete
repairs, mastic, crack seal, and asphalt patching work and seal coat, shall be completed in two (2) phases,
one (1) phase per day or as approved by the Project Manager to maximize access and parking to Treatment
Plant Staff. All work shall be coordinated with Castle Rock Water Department staff.
“Founder’s Treatment Plant” ” work shall take place during normal weekdays from 7a.m. - 5p.m. Concrete
work, mastic, crack seal, and asphalt patching shall be completed in a manner to maximize access and
parking. Seal coat shall be completed in one (1) phase per day or as approved by the Project Manager. All
work shall be coordinated with Castle Rock Water Department staff.
“Weaver II Well Field” work shall take place during normal weekdays from 7a.m. - 5p.m. Concrete work,
mastic, crack seal, and asphalt patching shall be completed in a manner to maximize access and parking.
Seal coat shall be completed in two (2) phases, one (1) phase per day or as approved by the Project Manager.
All work shall be coordinated with Castle Rock Water Department staff.
“Wrangler Parking Lot” Concrete work and asphalt patching shall be completed in a manner to maximize
access and parking work and shall take place during normal weekdays from 7a.m. – 5p.m. Seal coat shall
be completed in two (2) phases, one (1) phase per day or as approved by the Project Manager. All work
shall be coordinated with Parks and Recreation Department staff.
“Bison Park Parking Lot” work shall take place during normal weekdays from 7a.m. – 5p.m. The work to be
performed under this contract includes removal and replacement of existing concrete including concrete
pavement, crosspan, sidewalk, curb and gutter, curb ramps, asphalt patching, various depths and types of
milling of existing asphalt pavement, and various thicknesses of asphalt paving within the parking lot listed in
the Appendices or as directed by the Project Manager. All work shall be coordinated with Parks and
Recreation Department staff.
“Gemstone Park Parking Lot” work shall take place during normal weekdays from 7a.m. – 5p.m. Concrete
work and asphalt shall be completed in a manner to maximize access and parking. Perform full depth
reclamation, and various thicknesses of asphalt paving within the parking lot listed. All work shall be
coordinated with Parks and Recreation Department staff.
“Butterfield Park (Concrete off Meadows Blvd)” work shall take place during normal weekdays from 7a.m. –
5p.m. Concrete curb, gutter, and pavement work shall be completed in a manner to maximize access and
parking. All work shall be coordinated with Parks and Recreation Department staff.
The contractor shall commence work no later than three (3) calendar days from, and including, the date of
the Notice to Proceed, and be construction complete (punchlist items, cleanup, and demobilize) within thirtyfive
(45) working days from the date on the Notice to Proceed. All work shall take place during the timeframe
of September 5, 2023 – November 3, 2023.